Референции по золошлакоудалению для NTPC и энергокомпаний штатов
Здесь собраны проекты золошлакоудаления, введённые в эксплуатацию или реализуемые Macawber Beekay для NTPC и энергокомпаний индийских штатов.

Референции охватывают системы удаления золы-уноса, донной золы (шлака) и гидрозолоудаления, с конфигурацией проектов, производительностью систем и датами ввода в эксплуатацию или статусом реализации.
- 67projects listed
- 55commissioned
- 12under execution
- 24utilities and owners
- 800 MWlargest unit size
- 1999earliest commissioning listed
Register Project references
Each row is one project. Filter by owner, status, scope or unit size, or search for a plant, utility, state or EPC contractor. Select a row to see the fly ash, bottom ash and slurry disposal specifications.
In progressLara STPP, Stage II
Fly ash system
- System
- Dense phase pressure conveying to the fly ash classification system (Stage I), then to the fine and main fly ash silos (Stage II)
- Capacity
- Stage I: 319 TPH per unit (6 + 2 lines)Stage II: coarse ash 105 TPH per stream (3 working, 2 standby per unit); fine ash 152.5 TPH (1 working, 1 standby, both units)
- Conveying distance
- Stage I: 315 mStage II: 1,128 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps to dewatering bins
- Capacity
- 3 × 93 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 3 streams, 1,115 m³/h per unit (1 working, 2 standby)
- Pumping distance
- 1,334 m
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 6 × 133 TPH for both units (4 working, 2 standby)
- Pumping distance
- 6,500 m, 25.6 m static head
- Owner
- NTPC Limited
- Executed through
- BHEL-ISG, Bengaluru
- Current status
- Supplies 41%Erection 17%
In progressUkai Supercritical TPP
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying, ESP hoppers to main and intermediate silos
- Capacity
- 326 TPH
- Conveying distance
- 436 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 82 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash (to ash dyke, or dewatering bins for truck disposal)
- Pumping distance
- 3,000 m
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 2 × 142 TPH
- Pumping distance
- 3,000 m
- Owner
- Gujarat State Electricity Corporation Ltd.
- Executed through
- Dineshchandra R. Agrawal Infracon, Gurugram
- Current status
- Under engineering
In progressSingareni Thermal Power Project Extension
Fly ash system
- System
- Dense phase pressure conveying to the intermediate and HCSD silos (Stage I), then to the main fly ash silos (Stage II)
- Capacity
- Stage I: 319 TPH per unit (6 + 2 lines)Stage II: 6 streams of 107 TPH per unit (3 working, 3 standby)
- Conveying distance
- Stage I: 710 mStage II: 1,550 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps to dewatering bins or ash dyke
- Capacity
- 3 × 93 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 3 streams, 1,185 m³/h per unit (1 working, 2 standby)
- Pumping distance
- 4,000 m, 10 m static head
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 4 × 140 TPH (2 working, 2 standby)
- Pumping distance
- 4,500 m, 30 m static head
- Owner
- The Singareni Collieries Company Ltd.
- Executed through
- Power Mech Projects, Hyderabad
- Current status
- Under engineering
In progressDeen Bandhu Chhotu Ram TPP, Yamuna Nagar
Fly ash system
- System
- Vacuum extraction with pressure conveying
- Capacity
- Vacuum: 6 × 57.5 TPHPressure: 3 × 115 TPH
- Conveying distance
- 415 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 94 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash and fly ash
- Capacity
- 1,050 m³/h
- Pumping distance
- 8,000 m, 15 m static head
- Owner
- Haryana Power Generation Corporation Ltd.
- Executed through
- BHEL (PSNR), Noida
- Current status
- Under design and engineeringCivil works 5%
In progressUdangudi Super Thermal Power Plant, Stage I
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 95 TPH per unitStage II: 2 × 75 TPH
- Conveying distance
- Stage I: 500 mStage II: 1,250 m
Bottom ash system
- System
- Submerged scraper chain conveyor with jet pumps
- Capacity
- 2 × 20 TPH
- Owner
- Tamil Nadu Generation and Distribution Corporation Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Current status
- Supplies 99.5%Erection 80%
In progressBuxar Thermal Power Project
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 6 × 60 TPH per unitStage II: 3 × 120 TPH
- Conveying distance
- Stage I: 100 mStage II: 1,750 m
Bottom ash system
- System
- Water-impounded bottom ash hopper and jet pumps
- Capacity
- 3 × 73.66 TPH per unit
- Owner
- SJVN Thermal Pvt. Ltd.
- Executed through
- Larsen & Toubro, Vadodara
- Current status
- Supplies completeErection: Unit 1 and common systems complete, Unit 2 30%
In progressSagardighi Thermal Power Station
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 8 × 56 TPH per unitStage II: 5 × 112 TPH
- Conveying distance
- Stage I: 117 mStage II: 740 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 98 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 1,270 m³/h at 29 MWC
- Pumping distance
- 3,750 m
- Owner
- West Bengal Power Development Corporation Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Current status
- Supplies 100%Erection 98%
In progressTalcher TPP, Stage III (bottom ash and slurry package)
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 90 TPH
- Owner
- NTPC Limited
- Executed through
- BHEL-ISG, Bengaluru
- Current status
- Supplies 87%Under erection
- Note
- Ordered by BHEL for NTPC's plant
In progressKoradi TPP
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying
- Capacity
- 201.6 TPH
- Conveying distance
- 950 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 96 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 3 streams, 1,130 m³/h per unit (2 working, 1 standby)
- Pumping distance
- 3,500 m
- System
- Coarse ash slurry pumps
- Capacity
- 884 m³/h (1 working, 1 standby)
- Pumping distance
- 260 m
- System
- Fly ash slurry pumps
- Capacity
- 850 m³/h (1 working, 1 standby)
- Pumping distance
- 122 m
- System
- High concentration slurry disposal (HCSD)
- Capacity
- 236 m³/h at 60%, 210 m³/h at 65%, 188 m³/h at 70% concentration
- Pumping distance
- 3,500 m
- Owner
- Maharashtra State Power Generation Company Ltd.
- Executed through
- TKIL Industries, Pune
- Current status
- Under design and engineeringCivil works 5%
In progressKorba West
Fly ash system
- System
- Vacuum extraction with pressure conveying
- Capacity
- Vacuum: 6 × 42 TPHPressure: 3 × 84 TPH
- Conveying distance
- 925 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 84 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash (to ash dyke, or dewatering bins for truck disposal)
- Pumping distance
- 13,000 m
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 6 × 115 TPH
- Pumping distance
- 13,000 m
- Owner
- Chhattisgarh State Power Generation Company Ltd.
- Executed through
- BHEL (PSNR), Noida
- Current status
- Under design and engineering
In progressTalcher STPS, Stage II (ash slurry disposal to mine)
Mine void filling
- System
- Ash slurry disposal to mine voids, with ash water recovery (AWRS)
- Capacity
- 1,270 m³/h
- Pumping distance
- 1,100 m
- Owner
- NTPC Limited
- Current status
- Supplies 80%Under erection
In progressRihand Super Thermal Power Project, Stage I
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 60 TPH per unitStage II: 2 × 120 TPH
- Conveying distance
- Stage I: 40 mStage II: 900 m
- Owner
- NTPC Limited
- Current status
- Supplies 100%Erection 60%Civil works 72%
2025North Karanpura TPS
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 6 × 55.8 TPH per unitStage II: 3 × 111.6 TPH
- Conveying distance
- Stage I: 80 mStage II: 900 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps; bottom ash overflow (BAOF) slurry pumped to the dewatering bins or ash dyke
- Capacity
- 3 × 96 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 1,039 m³/h at 45 MWC
- Pumping distance
- 3,000 m
- System
- High concentration slurry disposal (HCSD)
- Capacity
- 163 m³/h
- Pumping distance
- 5,000 m
- Owner
- NTPC Limited
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 1: Feb 2023Unit 2: Feb 2024Unit 3: Jun 2025
2025Bhusawal TPS
Fly ash system
- System
- Two-stage dense phase pneumatic pressure conveying
- Capacity
- Stage I: 297 TPHStage II: 2 × 148 TPH
- Conveying distance
- Stage I: 250 mStage II: 650 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 90 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 2 streams of 1,250 m³/h (1 working, 1 standby)
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 2 × 193 TPH (1 working, 1 standby)
- Pumping distance
- 12,000 m, 72.5 m static head
- Owner
- Maharashtra State Power Generation Company Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Jan 2025
2024Wanakbori TPS
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 6 × 60 TPHStage II: 4 streams of 116 TPH per unit (3 working, 1 standby)
- Conveying distance
- Stage I: 70 mStage II: about 1,000 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 75 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 2 streams of 890 m³/h (1 working, 1 standby)
- Pumping distance
- 3,000 m, 15 m static head
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 2 × 200 TPH (1 working, 1 standby)
- Pumping distance
- 1,300 m, 15 m static head
- Owner
- Gujarat State Electricity Corporation Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 1: Mar 2023Unit 2: Feb 2024
2024Telangana Super Thermal Power Project, Karimnagar
Fly ash system
- System
- Two-stage dense phase pneumatic pressure conveying
- Capacity
- Stage I: 363 TPHStage II: 6 streams of 112.43 TPH per unit (3 working, 3 standby)
- Conveying distance
- Stage I: 130 mStage II: 1,150 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 109 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 3 streams, 1,510 m³/h for both units (1 working, 2 standby)
- Pumping distance
- 7,500 m, 30 m static head
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 6 × 129 TPH for both units (4 working, 2 standby)
- Pumping distance
- 11,000 m, 30 m static head
- Owner
- NTPC Limited
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 1: Mar 2023Unit 2: Feb 2024
2023Maitree Super Thermal Power Project, Rampal
Fly ash system
- System
- Pressure conveying in three stages, including ship loading from the main silos
- Capacity
- Stage I: 95 TPH per unitStage II: 2 × 75 TPH per unit (1 working, 1 standby)Stage III: 300 TPH common to both units, ship loading
- Conveying distance
- Stage I: up to 500 mStage II: 1,250 mStage III: 200 m
Bottom ash system
- System
- Pressure conveying from the bottom ash main silo to ship loading
- Capacity
- 2 × 300 TPH common to both units (1 working, 1 standby), 150 m
Slurry disposal and HCSD
- System
- Ash slurry disposal, bottom ash and fly ash
- Capacity
- 3 × 60 TPH dry ash basis, common to both units (2 working, 1 standby)
- Pumping distance
- 2,500 m
- Owner
- Bangladesh-India Friendship Power Company (Pvt.) Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 1: Oct 2022Unit 2: Dec 2023
2023Rihand Super Thermal Power Project, Stage III
Fly ash system
- System
- Dense phase pressure conveying (Stage II)
- Capacity
- 3 × 102 TPH per unit (2 working, 1 standby)
- Conveying distance
- 1,110 m
- Owner
- NTPC Limited
- Commissioning
- Dec 2023
2023Rourkela PP-II Expansion Project
Fly ash system
- System
- Two-stage dense phase pneumatic pressure conveying
- Capacity
- Stage I: 97 TPHStage II: 2 × 97 TPH (1 working, 1 standby)
- Conveying distance
- Stage I: 300 mStage II: about 1,150 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 65 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 3 streams of 630 m³/h (1 working, 1 standby, 1 maintenance standby), 2 pipelines
- Pumping distance
- 6,000 m, 39.5 m static head
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 2 × 90 TPH (1 working, 1 standby)
- Pumping distance
- 6,000 m, 39.5 m static head
- Owner
- NTPC-SAIL Power Company Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Mar 2023
2022Sri Damodaram Sanjeevaiah TPS, Krishnapatnam
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II); dense phase also for Stage III
- Capacity
- Stage I: 8 × 40 TPHStage II: 5 streams of 80 TPH (4 working, 1 standby)
- Conveying distance
- Stage I: 80 mStage II: 480 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps, dewatering bins (Hydrobins) and slurry pumps
- Capacity
- 3 × 75 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal, bottom ash
- Capacity
- 3 streams of 980 m³/h (1 working, 1 standby, 1 maintenance standby)
- Pumping distance
- 6,250 m, 21 m static head
- System
- High concentration slurry disposal (HCSD), fly ash
- Capacity
- 2 × 140 TPH (1 working, 1 standby)
- Pumping distance
- 6,250 m, 40 m static head
- Owner
- Andhra Pradesh Power Development Company Ltd.
- Executed through
- Tata Power, Hyderabad
- Commissioning
- Mar 2022
2021Sipat STPP, Stage I (augmentation of dry fly ash transportation, Units 2 & 3)
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 288 TPH per unit: 4 streams of 96 TPH (3 working, 1 standby)
- Conveying distance
- 935 m
- Owner
- NTPC Limited
- Commissioning
- Aug 2021
2017Yermarus Thermal Power Station, Raichur
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 6 × 66 TPH per unitStage II: 3 × 132 TPH
- Conveying distance
- Stage I: 70 mStage II: 850 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps; bottom ash overflow (BAOF) slurry pumped to the ash dyke
- Capacity
- 3 × 77 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 6 × 755 m³/h at 45.37 MWC
- Pumping distance
- 16,000 m
- Owner
- Raichur Power Corporation Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 1: Oct 2016Unit 2: Mar 2017
2017Bokaro A TPS
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 60 TPHStage II: 2 × 120 TPH
- Conveying distance
- 750 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 75 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 720 to 775 m³/h at 18 to 20 MWC
- Pumping distance
- 3 × 750 m
- Owner
- Damodar Valley Corporation
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Jan 2017
2017Parli TPP
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 45 TPHStage II: 4 × 45 TPH
- Conveying distance
- Stage I: 100 mStage II: about 1,000 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 65 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 650 m³/h at 50 MWC
- Pumping distance
- 2,500 m
- Owner
- Maharashtra State Power Generation Company Ltd.
- Executed through
- Sunil Hi-Tech Engineers, Nagpur
- Commissioning
- Mar 2017
2016Marwa Thermal Power Plant
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 60 TPHStage II: 2 × 120 TPH
- Conveying distance
- Stage I: 100 mStage II: about 1,000 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 75 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 620 m³/h at 47 MWC
- Pumping distance
- 7,000 m
- System
- High concentration slurry disposal (HCSD)
- Capacity
- 175 m³/h
- Owner
- Chhattisgarh State Power Generation Company Ltd.
- Executed through
- BGR Energy Systems, Chennai
- Commissioning
- Unit 1: Feb to Mar 2016 (COD)Unit 2: Jul to Aug 2016
2016Anpara D TPS
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying, with slurry disposal
- Capacity
- 2 × 230 TPH
- Conveying distance
- 600 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 82 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 965 m³/h at 49 MWC
- Pumping distance
- 3 × 14,000 m
- System
- Ash water recovery system (AWRS)
- Capacity
- 1,350 m³/h at 130 MWC
- Owner
- Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 6: May 2016Unit 7: Oct 2016
2016Chandrapur Expansion TPP
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying, with slurry disposal
- Capacity
- 240 TPH
- Conveying distance
- 510 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 75 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 975 m³/h at 47.5 MWC
- Pumping distance
- 2 × 15,000 m
- Owner
- Maharashtra State Power Generation Company Ltd.
- Executed through
- BGR Energy Systems, Chennai
- Commissioning
- Unit 8: Nov 2015Unit 9: Sep 2016
2015Vindhyachal Super Thermal Power Station, Stage V
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 48.67 TPHStage II: 2 × 97.33 TPH
- Conveying distance
- Stage I: 70 mStage II: about 1,050 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps, with ash water recovery (AWRS)
- Capacity
- 2 × 61.5 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 1,250 m³/h at 43.5 MWC
- Pumping distance
- 2 × 10,500 m
- Owner
- NTPC Limited
- Commissioning
- Sep 2015
2015Tuticorin TPP
Bottom ash system
- System
- Scraper chain conveyor
- Capacity
- 4 × 40 TPH
- Owner
- NLC Tamil Nadu Power Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 1: Mar 2015Unit 2: Jun 2015
2014Mouda Super Thermal Power Station
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 63.33 TPHStage II: 3 × 126.66 TPH
- Conveying distance
- Stage I: 70 mStage II: about 1,030 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 85 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 872 m³/h at 45 MWC
- Pumping distance
- 3 × 4,000 m
- System
- High concentration slurry disposal (HCSD), bottom ash and fly ash
- Capacity
- 190 TPH
- Pumping distance
- 4,000 m
- Owner
- NTPC Limited
- Commissioning
- Dec 2014
2014Chhabra TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- Stage I: 60 TPHStage II: 100 TPH
- Conveying distance
- Stage I: 365 mStage II: 1,000 m per stream
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Grasim Industries, Mumbai
- Commissioning
- Unit 3: Dec 2013Unit 4: Mar 2014
2014Korba West TPS (HTPS)
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 112 TPH per unit
- Conveying distance
- 600 to 850 m (Unit 1: 600 mUnit 2: 640 mUnit 3: 800 mUnit 4: 850 m)
Bottom ash system
- System
- Dewatering bins (Hydrobins) with sedimentation and settling tanks; bottom ash and fly ash then go to HCSD
Slurry disposal and HCSD
- System
- High concentration slurry disposal (HCSD)
- Capacity
- 175 m³/h
- Pumping distance
- 12,000 m
- Owner
- Chhattisgarh State Power Generation Company Ltd.
- Commissioning
- Fly ash: Units 1 & 2 May 2011, Unit 3 Aug 2011, Unit 4 Nov 2011HCSD: Dec 2013 to Jan 2014
2013Kalisindh TPP
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying
- Capacity
- 210 TPH
- Conveying distance
- 800 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 3 × 60 TPH
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Wonder Cement (fly ash); BGR Energy Systems (bottom ash)
- Commissioning
- Sep 2013
- Note
- Operation and maintenance by Macawber Beekay.
2013Kalisindh TPP
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying
- Capacity
- 210 TPH
- Conveying distance
- 700 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Ambuja Cement (fly ash); BGR Energy Systems (bottom ash)
- Commissioning
- Dec 2013
- Note
- Operation and maintenance by Macawber Beekay.
2013Ukai TPP
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying
- Capacity
- 210 TPH
- Conveying distance
- 300 m
Bottom ash system
- System
- Submerged scraper chain conveyor, belt conveyor and disposal
- Capacity
- 2 × 45 TPH
- Owner
- Gujarat State Electricity Corporation Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Bottom ash: Dec 2012Fly ash: Mar to Apr 2013
- Note
- Operation and maintenance by Macawber Beekay.
2012Mettur TPP
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 73.5 TPHStage II: 2 × 147 TPH
- Conveying distance
- Stage I: 80 mStage II: 900 m
Bottom ash system
- System
- Dry bottom ash conveyor (DRYCON)
- Capacity
- 45 TPH normal, 90 TPH design
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 460 m³/h at 42 MWC
- Pumping distance
- 4,000 m
- Owner
- Tamil Nadu Electricity Board
- Executed through
- BGR Energy Systems, Chennai
- Commissioning
- Nov 2012 (COD Dec 2012)
2012Sikka TPP, Jamnagar
Fly ash system
- System
- Single-stage dense phase pneumatic pressure conveying, with slurry disposal
- Capacity
- 30.2 TPH per stream (4 streams)
- Conveying distance
- 900 m
Bottom ash system
- System
- Submerged scraper chain conveyor, belt conveyor and disposal
- Capacity
- 4 × 5 TPH
- Owner
- Gujarat State Electricity Corporation Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Dec 2012
2012Korba East TPS
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Units 1 to 4: 50 TPHUnits 5 & 6: 60 TPH
- Conveying distance
- Stage I: 60 mStage II: 500 m
Bottom ash system
- System
- Dewatering bins with sedimentation and settling tanks; bottom ash and fly ash then go to HCSD
Slurry disposal and HCSD
- System
- High concentration slurry disposal (HCSD)
- Capacity
- 135 m³/h
- Pumping distance
- 9,500 m
- Owner
- Chhattisgarh State Power Generation Company Ltd.
- Commissioning
- Fly ash: May to Nov 2011HCSD: Sep 2012
2011Suratgarh TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 100 TPH
- Conveying distance
- 200 m
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Grasim Cement and Shree Cement
- Commissioning
- Jan 2011
2011Korba West TPS (renovation)
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Units 1 to 4: 50 TPHUnits 5 & 6: 60 TPH
- Conveying distance
- Stage I: 60 mStage II: 500 m
- Owner
- Chhattisgarh State Power Generation Company Ltd.
- Commissioning
- Units 1 & 2: May 2011Units 3 & 4: Aug and Nov 2011
2011Obra TPP
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- Unit 9: 54 TPH
- Conveying distance
- 300 m
- Owner
- Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Jaiprakash Associates, Noida
- Commissioning
- Mar 2011
2011Sikka TPP
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- Stage I: 2 × 20 TPHStage II: 2 × 35 TPH
- Conveying distance
- Stage I: 150 mStage II: 1,550 m
- Owner
- Gujarat State Electricity Corporation Ltd.
- Executed through
- Shree Digvijay Cement, Jamnagar
- Commissioning
- Jan 2011
2011Kothagudem TPS, Stations A, B & C
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 42 TPH per unit (Units 1 to 4), 2 × 45 TPH per unit (Units 5 to 8)Stage II: 50 TPH per unit (Units 1 to 4), 100 TPH (Units 5 to 8)
- Conveying distance
- Stage I: 80 to 90 mStage II: 1,000 m (Units 1 to 4), 1,200 m (Units 5 to 8)
- Owner
- Andhra Pradesh Power Generation Corporation Ltd.
- Commissioning
- Units 1 to 4: Jun to Dec 2010Units 5 to 8: Jun to Oct 2011
2010Chhabra TPS
Fly ash system
- System
- Dry fly ash collection and transportation
- Capacity
- Stage I: 75 TPH per unitStage II: 112 TPH per unit
- Conveying distance
- 1,000 m
Bottom ash system
- System
- Scraper chain conveyor
- Capacity
- 36 TPH
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Grasim Industries and Shree Cement (fly ash); Punj Lloyd (bottom ash)
- Commissioning
- Unit 1: Oct 2009Unit 2: May 2010
2010Suratgarh STPP
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 100 TPH
- Conveying distance
- 200 m
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Shree Cement, Beawar
- Commissioning
- Jan 2010
2010Rayalaseema TPP, Stage III
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 45 TPHStage II: 2 × 90 TPH
- Conveying distance
- Stage I: 75 mStage II: 1,200 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 65 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 240 m³/h at 41 MWC
- Pumping distance
- 5,500 m
- Owner
- Andhra Pradesh Power Generation Corporation Ltd.
- Commissioning
- Nov 2010
2010Panipat TPS
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 2 × 30 TPH per 110 MW unit, 4 × 30 TPH for the 210 MW unitStage II: 60 TPH per unit
- Conveying distance
- Stage I: 100 mStage II: 1,300 m
- Owner
- Haryana Power Generation Corporation Ltd.
- Executed through
- Jaiprakash Associates, Noida
- Commissioning
- Unit 5: Mar 2010Unit 4: May 2010Unit 3: Jul 2010
2009Giral Lignite TPP
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 65 TPH
- Conveying distance
- 760 m
Bottom ash system
- System
- Bed ash by scraper chain conveyor
- Capacity
- 20 TPH
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Tata Power, Hyderabad
- Commissioning
- Jan 2009
2008Chandrapur TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- Stage I: 70 TPHStage II: 70 TPH
- Conveying distance
- Stage I: 250 mStage II: 700 m
- Owner
- Maharashtra State Electricity Board
- Executed through
- UltraTech Cement, Mumbai
- Commissioning
- Jun 2008
2008Guru Hargobind TPP, Lehra Mohabbat
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 2 × 120 TPH
- Conveying distance
- 320 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 60 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 700 m³/h at 41 MWC
- Pumping distance
- 2 × 2,000 m
- Owner
- Punjab State Electricity Board
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Unit 3: Jan 2008Unit 4: Jul 2008
2008Mejia TPS (Boilers 1, 2 & 3)
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- Stage I: 3 × 37.5 TPHStage II: 100 TPH
- Conveying distance
- 1,600 m
- Owner
- Damodar Valley Corporation
- Executed through
- Lafarge India, Kolkata
- Commissioning
- Jun 2008
2008Rayalaseema TPP, Stage II
Slurry disposal and HCSD
- System
- Ash slurry disposal (design, supply, erection and commissioning)
- Capacity
- 68 TPH per stream, 2 streams (80 m³/h)
- Pumping distance
- 15,000 m
- Owner
- Andhra Pradesh Power Generation Corporation Ltd.
- Commissioning
- Sep 2008
2008Giral Lignite TPP
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 65 TPH
- Conveying distance
- 600 m
Bottom ash system
- System
- Bed ash by drag chain conveyor
- Capacity
- 20 TPH
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Commissioning
- May 2008
2007Kota TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 80 TPH
- Conveying distance
- 1,250 m
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Birla Corporation, Chanderia
- Commissioning
- May 2007
2007Rayalaseema TPP
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 90 TPH per stream
- Conveying distance
- 1,800 m
- Owner
- Andhra Pradesh Power Generation Corporation Ltd.
- Commissioning
- Jun 2007
2007Kota TPS
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 2 × 30 TPHStage II: 50 TPH
- Conveying distance
- Stage I: 170 mStage II: 1,500 m
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- ACC, Mumbai
- Commissioning
- Apr 2007
2006Kota TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- Stage I: 80 TPHStage II: 100 TPH
- Conveying distance
- 750 m
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- Grasim Industries, Mumbai
- Commissioning
- Unit 5: Aug 2006Unit 4: Oct 2006
2005Chandrapur TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 62 TPH
- Conveying distance
- about 900 m
- Owner
- Maharashtra State Electricity Board
- Executed through
- ACC (Chanda Cement Works)
- Commissioning
- Dec 2005
2005Bandel TPP
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- 2 × 35 TPH and 2 × 50 TPH
- Conveying distance
- Stage I: 100 to 120 mStage II: 550 m
- Owner
- West Bengal Power Development Corporation Ltd.
- Commissioning
- Aug 2005
2003Mettur TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 50 TPH
- Conveying distance
- 520 m
- Owner
- Tamil Nadu Electricity Board
- Executed through
- ACC, Mumbai
- Commissioning
- Feb 2003
2003Mettur TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 80 TPH
- Conveying distance
- 525 m
- Owner
- Tamil Nadu Electricity Board
- Executed through
- Grasim Cement, Mumbai
- Commissioning
- Oct 2003
2003Mettur TPS
Fly ash system
- System
- Dense phase pneumatic pressure conveying
- Capacity
- 60 TPH
- Conveying distance
- 350 m
- Owner
- Tamil Nadu Electricity Board
- Executed through
- Chettinad Cement, Tamil Nadu
- Commissioning
- Dec 2003
2001Khaperkheda TPS
Bottom ash system
- System
- Water-impounded bottom ash hopper and jet pumps
- Capacity
- 4 × 60 TPH (2 working, 2 standby)
- Owner
- Maharashtra State Electricity Board
- Commissioning
- May 2000 to Jan 2001
1999Raichur TPS
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 3 × 30 TPHStage II: 70 TPH
- Conveying distance
- Stage I: 85 mStage II: 950 m
- Owner
- Karnataka Power Corporation Ltd.
- Executed through
- ACC (P&E Division), Thane
- Commissioning
- Aug 1999
—Suratgarh Super Critical TPP
Fly ash system
- System
- Two-stage dense phase pneumatic pressure conveying
- Capacity
- Stage I: 260 TPHStage II: 2 × 130 TPH
- Conveying distance
- Stage I: 550 mStage II: about 1,200 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 120 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 965 m³/h at 46 MWC
- Pumping distance
- 4 × 4,000 m
- Owner
- Rajasthan Rajya Vidyut Utpadan Nigam Ltd.
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Commissioned
—New Neyveli Lignite TPP
Fly ash system
- System
- Vacuum extraction (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 86 TPH, ESP to buffer hopperStage II: 86 TPH, buffer hopper to main silo
- Conveying distance
- Stage I: 150 mStage II: 1,000 m
Bottom ash system
- System
- Water-impounded hopper with submerged scraper chain conveyor and belt conveyor
- Capacity
- 97 TPH wet; belt conveyor 45 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 1,250 m³/h at 40 MWC
- Pumping distance
- 3,000 m
- Owner
- Neyveli Lignite Corporation Ltd.
- Executed through
- Essar Projects India, Mumbai
- Commissioning
- Commissioned
—Barauni TPP
Fly ash system
- System
- Vacuum extraction by mechanical exhauster (Stage I), then dense phase pressure conveying (Stage II)
- Capacity
- Stage I: 4 × 66 TPHStage II: 2 × 132 TPH
- Conveying distance
- Stage I: 150 mStage II: 550 m
Bottom ash system
- System
- Water-impounded bottom ash hopper, jet pumps and slurry pumps
- Capacity
- 2 × 60 TPH
Slurry disposal and HCSD
- System
- Lean slurry disposal
- Capacity
- 630 m³/h at 38 MWC
- Pumping distance
- 6,000 m
- Owner
- Bihar State Electricity Board
- Executed through
- BHEL-ISG, Bengaluru
- Commissioning
- Commissioned
Как читать список
Каждая строка — один проект: год ввода в эксплуатацию (или «В работе»), электростанция, владелец, конфигурация энергоблоков и штат. Метки показывают, какие системы поставила Macawber Beekay. Откройте строку, чтобы увидеть спецификацию каждой системы и даты ввода в эксплуатацию по блокам.
- Система золы-уноса: как сухая зола-унос транспортируется из бункеров ESP, воздухоподогревателя и экономайзера в силосы, с производительностью и дальностью транспортировки. См. удаление золы-уноса.
- Система донной золы: как крупная зола удаляется из-под котла, с указанием производительности. См. удаление донной золы.
- Гидрозолоудаление и HCSD: как зола перекачивается на золоотвал или в горную выработку в виде низкоконцентрированной или высококонцентрированной пульпы, с производительностью насосов и длиной пульпопровода. См. гидрозолоудаление.
- Через кого выполнен: если заказ поступил через EPC-подрядчика или через цементную компанию, она указана здесь.
Термины в спецификациях
| Термин | Значение |
|---|---|
| TPH | Тонн в час: производительность транспортировки сухой золы |
| m³/h | Кубических метров в час: производительность перекачки пульпы |
| MWC | Метров водяного столба: напор насоса |
| Stage I / Stage II | Двухступенчатые системы золы-уноса: Stage I собирает золу из бункеров в буферный или промежуточный силос, Stage II транспортирует её в основные силосы |
| Рабочие / резервные | Сколько линий или насосов работают одновременно и сколько держится в резерве |
| HCSD | Высококонцентрированное гидрозолоудаление: зола перекачивается с высоким содержанием твёрдого и гораздо меньшим расходом воды |
| AWRS | Система возврата осветлённой воды: возвращает воду с золоотвала или золового пруда |
| BAOF | Перелив системы донной золы: пульпа из системы донной золы, перекачиваемая на золоотвал или в обезвоживающие бункеры |
| Статический напор | Разность высот, которую должен преодолеть пульпопровод |
| COD | Дата начала коммерческой эксплуатации |
Что показывает список
- Энергоблоки от 50 MW до 800 MW. Самый ранний проект, Raichur TPS для KPCL, введён в эксплуатацию в августе 1999 года. Последние заказы относятся в основном к блокам 660 MW и 800 MW.
- Транспортировка золы-уноса на расстояние до 1 800 м (Rayalaseema TPP для APGENCO) и двухступенчатые системы, в которых Stage I транспортирует до 363 TPH (Telangana STPP для NTPC).
- Пульпопроводы длиной до 16 000 м (Yermarus Thermal Power Station, Райчур) и пульпопроводы HCSD длиной 12 000 м на Bhusawal и Korba West; для Korba West 2 × 660 MW проектируется 13 000 м.
- Складирование золы в отработанных горных выработках на NTPC Talcher Stage II, с возвратом осветлённой воды.
Читайте также
- Система золошлакоудаления: комплексные установки — от котла до силоса
- Система золошлакоудаления для электростанции мощностью 800 MW
- Кейс: удаление шлака струйным насосом и золы-уноса вакуумным и напорным пневмотранспортом для пылеугольного котла
- Заполнение горных выработок золовой пульпой
- Заказчики Macawber Beekay
Дата последней проверки
Проконсультироваться с нашими инженерами
Наша инженерная группа в Нойде ответит на запросы по любой создаваемой нами системе.
Связаться с нами+91 120 450 7700Вопросы, которые задают заказчики
Для каких электростанций NTPC Macawber Beekay построила системы золошлакоудаления?
Среди введённых в эксплуатацию объектов NTPC — Mouda (2 × 500 MW), Vindhyachal Stage V (1 × 500 MW), расширение системы сухого удаления золы-уноса на Sipat Stage I (3 × 660 MW), Rihand Stage III (2 × 500 MW), Telangana STPP (2 × 800 MW) и North Karanpura (3 × 660 MW), а также NSPCL (NTPC-SAIL Power Company) в Rourkela и проект Maitree компании BIFPCL в Бангладеш. Lara Stage II, Talcher и Rihand Stage I находятся в стадии реализации.
Какие энергокомпании штатов входят в референц-лист Macawber Beekay?
Среди заказчиков на уровне штатов — RRVUNL (Раджастхан), MAHAGENCO и бывшая MSEB (Махараштра), GSECL (Гуджарат), CSPGCL (Чхаттисгарх), APGENCO и APPDCL (Андхра-Прадеш), TNEB и TANGEDCO (Тамилнад), UPRVUNL (Уттар-Прадеш), HPGCL (Харьяна), WBPDCL (Западная Бенгалия), KPCL и Raichur Power Corporation (Карнатака), Bihar State Electricity Board, PSEB (Пенджаб) и SCCL (Телангана).
Поставляла ли Macawber Beekay системы высококонцентрированного гидрозолоудаления (HCSD)?
Да. Пятнадцать проектов из списка включают HCSD, в том числе Korba West и Korba East для CSPGCL, NTPC Mouda, Telangana STPP и North Karanpura, Wanakbori для GSECL, Bhusawal для MAHAGENCO и NSPCL Rourkela. Пульпопроводы HCSD в списке имеют длину до 12 000 м — на Bhusawal и Korba West, а на проекте Korba West 2 × 660 MW, который сейчас проектируется, — 13 000 м.
Какую мощность энергоблоков охватывают эти референции?
Список охватывает энергоблоки от 50 MW на Korba East до 800 MW на Yermarus, Wanakbori, Krishnapatnam, Telangana STPP и Lara. Последние заказы относятся в основном к блокам 660 MW и 800 MW, а самый ранний проект в списке, Raichur TPS для KPCL, введён в эксплуатацию в августе 1999 года.
Ознакомьтесь со смежными системами.
Удаление золы-уносаСистемы удаления золы-уноса из бункеров ESP, воздухоподогревателя и экономайзера в силосы напорным пневмотранспортом в плотной фазе или вакуумом, с клапанами Dome Valve.
ШлакоудалениеСистемы удаления донной золы (шлака) для пылеугольных котлов и котлов ЦКС: струйные насосы, погружной скребковый конвейер (SSCC), сухие и пневматические системы.
ГидрозолоудалениеСистемы гидрозолоудаления: низкоконцентрированная пульпа с возвратом воды и высококонцентрированная пульпа (HCSD) при концентрации около 60% на расстояние до 17 км.
ЗаказчикиЗаказчики Macawber Beekay — энергокомпании, EPC-подрядчики, металлургические и цементные компании, в том числе NTPC, BHEL, Tata Power, Adani, Vedanta и ACC.
Проконсультироваться с нашими инженерами.
Планируете строительство нового объекта или модернизацию действующего? Наша инженерная группа в Нойде готова помочь.